Construction Schedule

Construction Task

Start

Finish

Access Roads to Turbine Sites Oct 2016 Jun 2017
Operations & Maintenance Facility Dec 2016 May 2017
Turbine Foundations Oct 2016 Jul 2017
Substation Oct 2016 Jun 2017
Underground Collection System Oct 2016 Jun 2017
Turbine Deliveries (average 5 per week) Jun 2017 Jul 2017
Turbine Installation Jun 2017 Aug 2017
Turbine Commissioning Jul 2017 Sep 2017
Land Restoration Jul 2017 Sep 2017